COLUMBUS, OHIO · POWER AND TAX

AEP Ohio, the data center tariff, and a few racks in Columbus

Central Ohio rewrote the rules for data center power in 2025. Almost none of it applies to a small tenant, and it still affects what you are offered.

What happened

AEP Ohio, the utility for central Ohio, stopped signing new data center service agreements while regulators considered how such large customers should pay for the grid they need. On July 9, 2025 the Public Utilities Commission of Ohio approved a new tariff and ordered the utility to lift the moratorium as soon as possible. PUCO

Under it, large new data center customers must pay for at least 85% of the energy they subscribe to, whether or not they use it, for 12 years including a four-year ramp-up. AEP The tariff applies to data centers and expansions of 25,000 kW or more. AEP Ohio

How much demand is behind it

Signed under the new tariff
5,642 MW as of February 12, 2026.
Signed before it
12,219 MW.
Total contracted
17,861 MW, scheduled to come online progressively through 2035.
For scale
Peak demand across all AEP Ohio customers has ranged between about 8,000 and 10,500 MW.

All four figures: AEP Ohio, February 2026.

What it means if you rent a rack

A rack uses a few kilowatts. The tariff's threshold is 25,000. You will never see this tariff on a bill.

The effects are second-hand, and this is our reading of them. A retail colocation building that wants to expand now has to commit to its utility for more than a decade, so operators are careful about promising growth. And capacity that is already energized has become the scarce thing in the region. In practice:

  • If you expect to grow, ask the provider what power it has available today, not what it plans.
  • Ask how the power component of your bill can change during the term.
  • At renewal, expect the provider to know its space is harder to replace than it was. A second quote helps; see renewals.

Ohio's average commercial electricity price was 10.95 cents per kWh in OH (state average commercial price, July 2026, EIA Electric Power Monthly).

Ohio's data center sales tax exemption

Ohio law allows a sales tax exemption on computer data center equipment where the project involves a capital investment of at least $100 million and annual payroll of at least $1.5 million at the site. The exemption can extend to other taxpayers that operate a data center business at the project site under the same agreement. Ohio Revised Code 122.175

Two things to know before counting on it. The legislature voted to end part of the program in the 2025 budget and the governor vetoed that change. WVXU, August 2025 Then in May 2026 the governor ordered a freeze on new requests while a legislative committee studies data centers. WOSU, May 2026

For a tenant with a few racks the practical answer is: ask the operator whether its site has an agreement that covers tenants, and treat any saving as a bonus. This is a description of the statute and the news, not tax advice.

And the weather

Central Ohio has no hurricanes and little seismic history to plan around, but it does get severe wind. The derecho of June 29, 2012 produced a 71 mph gust in Columbus. National Weather Service Ask how long a site can run on generator and when that was last tested under load.

Power and tax questions

Is there a moratorium on data centers in Columbus?

AEP Ohio paused new data center agreements in central Ohio; in July 2025 the PUCO approved a data center tariff and ordered the moratorium lifted. Small colocation tenants were never the subject of it.

What is the AEP Ohio data center tariff?

A rate structure for data centers of 25,000 kW or more that requires them to pay for at least 85% of the energy they subscribe to for 12 years, including a four-year ramp-up.

Do colocation tenants get Ohio's data center tax exemption?

Only if the facility has an agreement with the state that extends to tenants operating there. New requests were frozen in May 2026. Ask the operator and a tax professional.

Have power availability confirmed in writing with your quotes.